Enterprise Products Mansfield Compressor Pleasant Hills, LA Installation of 6 – 8,100 HP gas compressors and gathering system Completed on scheduled completion date.

close



2012
B-MAC COMPANY
more_vert

Energy Transfer Partners 200 Million Kenedy #1 Cryo Gas Plant, Kenedy, TX Installed 200 Million Cryo Gas Plant and storage facility. Completed on scheduled completion date.

close






2014
B-MAC COMPANY
more_vert

Enterprise Products Logansport Compressor Station Logansport, LA Relocate compressor station and dehi. Completed on scheduled completion date.

close






2014 - 2015
B-MAC COMPANY
more_vert

Energy Transfer Partners 200 Million Kenedy #2 Cryo Gas Plant, Kenedy, TX. Installed second 200 Million Cryo Gas Plant in parallel with plant #1 Completed ahead of scheduled completion date.

close








2015
B-MAC COMPANY
more_vert

Enterprise Products Belvieu Environmental Fuels (BEF) turnaround and revamp. Installed new cooling water system, 3 hot oil heaters, 20,000 HP electric motor. For Gas turbine, new lube oil system, and new Contact Cooler. Completed on scheduled completion date.

close








2016 - 2017
B-MAC COMPANY
more_vert

Enterprise Products Propane Dehydrogenation (PDH) Mont Belvieu, TX. Provided labor to assist Optimized Process Designs to construct a new Propane. Dehydrogenation Unit to make propylene for plastic.